Downstream excavation confinement
Downstream excavation confinement
For the project "Refurbishment of Viereth weir - gate replacement", the lack of an "n-1" condition on the Viereth weir resulted in an excavation...
Complete refurbishment of Mittelweser weir systems
Complete refurbishment of Mittelweser weir systems
In the area of Mittelweser, the complete refurbishment of five existing weirs (Petershagen (PHG), Schlüsselburg (SBG), Drakenburg (DBG), Dörverden...
Lock repair
Lock repair
Gerlachshausen lock is located on the river Main upstream of Würzburg. It was constructed in 1956 and commissioned in 1957. The chamber width is 12 m. The lock is fitted with mitre gates...
Complete refurbishment of Würzburg weir
Complete refurbishment of Würzburg weir
In the framework of the complete refurbishment of the right-hand weir of the Würzburg barrage, IRS and KREBS+KIEFER Karlsruhe were responsible for overall...
Pumped storage scheme Waldeck I
Pumped storage scheme Waldeck I
E.ON Wasserkraft operates the pumped storage schemes Waldeck I and Waldeck II near the Edersee lake.
At the time the survey was made, the pumped storage scheme...
Megolo power station - trashrack cleaning machine
Megolo power station - trashrack cleaning machine
The run-of-river power station of Megolo was completely refurbished by ANDINO Hydropower Engineering S.à.r.l.. In the course of the refurbishment...
Repair of Limbach weir
Repair of Limbach weir
Due to a ship collision on the weir of Limbach Mitte, the load-bearing effect of the damaged gate (30 m wide triple-braced gate with flap) had to be assessed, and the repair of...
Complete refurbishment of left lock chamber
Complete refurbishment of left lock chamber
In 2010, a beam floating on the river Neckar damaged the left chamber of the twin lock, which had been in operation for over 50 years. Due to its...
Lock of Xayaburi dam
Lock of Xayaburi dam
Xayaburi dam is currently under construction; it is a dam with a hydropower station and a navigation lock on Mekong river in Sainyabuli province in the north of Laos. The...
Planning of standardised mitre gates
Planning of standardised mitre gates
The river Neckar was developed into a federal waterway on a length of 203 km between 1921 and 1968. Upstream of Stuttgart, the 27 locks on the barrages, whose...
Search results 21 until 30 of 67